BuildingCape Town2026

The Granger Building, Cape Town

249 tonnes of reinforcing steel fixed for the biggest pour WBHO Cape has ever done.

Main contractorWBHO
Pour date14 September 2026
RMS branchCape Town (Blackheath)
Aerial view of The Granger Building construction site next to the stadium in Green Point, Cape Town
249t
1,312m³
13hours
217
24,451
Figures from WBHO and RMS Cape Town.
The project

249 tonnes, one pour: ready for concrete at The Granger

The Granger Building in Green Point, next to the stadium, was the biggest concrete pour WBHO Cape has ever done: 1,312 m³ in a single 13-hour pour, three planned pours consolidated into one.

WBHO cut the slab cycle from the usual 12 to 15 days to 11, and RMS Cape Town had to cut, bend, deliver and fix the full 249 tonnes inside that window: 24,451 bars in four to six layers across 2,160 m² of slab between 280 mm and 1,350 mm deep. RMS delivered. The team worked through both weekends, 9 days in total at about 29 tonnes a day, and the slab was ready for concrete on the morning of 14 September.

01

The challenge

A slab of this size and this programme leaves no room for steel that arrives late, in the wrong shape or in the wrong order. Final preparation ran through Sunday 13 September and the early hours of Monday, in wet weather, ahead of a 07:00 start.

02

What RMS did

RMS Cape Town cut and bent the reinforcement to the bending schedules at its Blackheath facility, delivered it in step with the fixing programme, and fixed it with a team of 104 steel fixers and 32 foremen under four RMS managers. When the programme looked out of reach, the branch drew on experience from across the RMS group to plan and resource the work. Production, delivery and fixing from one company gave WBHO a single point of contact while the dates were tight.

The RMS team

140 people. One project-specific team. 249 tonnes.

A project-specific team was mobilised for this pour: 104 steel fixers and 32 foremen under four RMS managers, supplied and fixed from the RMS Cape Town branch in Blackheath, about 36 km from site. Teams and rates are scaled to each project. Through both weekends, into the early hours of pour day. This one is for them.

104
32
4
36km
Northern CapeWestern CapeNorth WestFree StateGautengMpumalangaLimpopoKwaZulu-NatalEastern CapeJohannesburgRMS Cape Town (Blackheath)Port ElizabethEast LondonDurbanKathuBloemfonteinNelspruitPolokwaneThe Granger Building, Green Point
ProjectRMS branches
Where

Green Point, Cape Town

Supplied and fixed from the RMS Cape Town branch in Blackheath, about 36 km from site. Nine RMS branches cover South Africa, so projects are served from the nearest yard.

Nearest branchRMS Cape Town
ProvinceWestern Cape
Cut and bendBlackheath facility
DeliveryPaced to the fixing programme
RMS Cape Town branch
How RMS delivered it

From the Blackheath yard to the last bar on the slab

Production, delivery and fixing from one company, so the people who bent the steel and the people fixing it were on the same phone call.

RMS Cape Town team with bundled reinforcing steel at the Blackheath cut and bend facility
01

Cut and bend

Fabricated to the bending schedules at the Blackheath facility, with material certificates to SANS 920.

RMS delivery truck with reinforcing steel being offloaded at The Granger Building site in Green Point
02

Delivery

Bundles delivered in the sequence the fixing team needed them, lifted straight onto the slab.

RMS steel fixers tying reinforcing steel on The Granger Building slab
03

Steel fixing

The RMS team placing and tying 249 tonnes in four to six layers, under RMS site supervision.

Aerial view of boom pumps placing concrete on The Granger Building slab
04

The pour

1,312 m³ placed in a single 13-hour pour, from 217 trucks, over steel that had been checked bar by bar.

RMS team checking the reinforcement drawings before dawn on the day of the concrete pour
Pour day

The last sixteen hours

  • Sunday 13 September

    Pre-pour planning meeting with WBHO and the site teams.

  • Sunday 13 September

    RMS fixers still on the slab, finishing the last mats and checks.

  • Monday 14 September

    Night crews on the slab, three hours before the first pump.

  • Monday 14 September

    Concrete starts. Boom pumps running across the full 2,160 m².

  • Monday 14 September

    Pour complete. 1,312 m³, 217 trucks, 13 hours.

RMS steel fixers in branded orange vests checking the reinforcement mat at The Granger Building, Cape Town
Watch: WBHO on RMS 0:52
“
They are committed to the job, they have got strong people, their supervision is very good, they understand their planning, their resourcing, and they are always willing to come to the party and help WBHO meet their dates.
WBHO site management, The Granger Building
Talk to the branch

Planning a large pour in the Western Cape?

Send RMS Cape Town your drawings and bending schedules early. The earlier the cut and bend is planned, the more certain the delivery and the fixing programme.

RMS Cape Town27 Range Road, BlackheathMon to Thu 07:30 to 16:30, Fri 07:30 to 14:30